Test the Tenant based application flow in all modules will note the issues & assign to the team

Added by Yalavarthi Thriveni about 1 month ago. Updated about 1 month ago.

Status:
Closed
Priority:
Normal
Target version:
-
Start date:
07/01/2026
Due date:
07/01/2026
% Done:

100%

Estimated time:
Spent time:

Add

Subtasks


Add

Related issues

Updated by Yalavarthi Thriveni about 1 month ago

  • Status changed from New to In Progress
  • % Done changed from 0 to 50

Checked some pages & assign to team members
currently working on reducing of the customer list page load time,

Updated by Yalavarthi Thriveni about 1 month ago

  • Due date set to 07/01/2026
  • Status changed from In Progress to Closed
  • % Done changed from 50 to 100

I took customers page and updated customer list with the indexes, removal of unwanted promises to increase the api load
written populate function

Updated to Ravindra as well as Hr about the team updates
Currently Teja is working on Deejivo edge cases (validation ) issues for split payment , cancellation payment issues which he required tomorrow also
Divya is testing subscription end to end flow with tenant based to be work properly will required tomorrow
Sai teja is working on deleted list sort functionality & add some optimisations in the list api's to get the response quick
Ravi Shankar & Chandra shekar working on the landscaping flow with tenant code base & we have some known issues will continue the work furthur 2 days
Sowjanya, Karthik will work on some pages to be test & any issues will raise by mahanand
I asked Mahanand to be test on locally with subscription branch page to page
then will assign the issues to team members
I tested some pages & updates findings(issues) to karthik to work & discuss with chandra shekar on some queries in landscaping flows & some issues in UI level
Added Lazy loading for all the routes , don't load all the components on page load, now application is not taking much time to load
pavan will work on sub domain integration tomorrow and in e-commerce end to end all with tenant based testing

Edit Copy Actions