Feature #8014

open

4:00 hours on mail project template and next 4:00 hours on dispatch hub technical stack

Added by Yogeesh sai 14 days ago. Updated 13 days ago.

Status:
New
Priority:
Normal
Assignee:
Start date:
03/03/2026
Due date:
03/03/2026 (14 days late)
% Done:

100%

Estimated time:
8:00 h
Spent time:

Description

adding jwt key in .env and should show working project live by 12:30 and dispatch hub on technical knowledge to work on


Add

Subtasks


Add

Related issues

Updated by Yogeesh sai 14 days ago

Doing on the another 2 projects related to the dispatch hub and did a technical documentation related to dispatch hub technical part for better understanding to me.

Updated by Yogeesh sai 13 days ago

because of the secret keys in .env file of the mail project template and my work was delayed this work is for 4 hours and next 4 hours on technical stack on dispatch hub

Actions #3

Updated by Yogeesh sai 13 days ago

  • Due date changed from 03/03/2026 to 03/04/2026
Actions #4

Updated by Yogeesh sai 13 days ago

  • Estimated time changed from 8:00 h to 16:00 h
Actions #5

Updated by Yogeesh sai 13 days ago

  • Due date changed from 03/04/2026 to 03/03/2026

Updated by Yogeesh sai 13 days ago

  • Estimated time changed from 16:00 h to 8:00 h

Completed the mail project template related to dispatch hub and got the knowledge on the technical stack of dispatch hub.

Actions #7

Updated by Yogeesh sai 13 days ago

  • % Done changed from 0 to 100