Review the delivery module flow which will be noted by Teja & verify with Sai sir & get approval from Client

Added by Yalavarthi Thriveni 17 days ago. Updated 16 days ago.

Status:
Closed
Priority:
Normal
Target version:
-
Start date:
09/01/2026
Due date:
09/01/2026
% Done:

100%

Estimated time:
Spent time:

Add

Subtasks


Add

Related issues

Updated by Yalavarthi Thriveni 16 days ago

  • Due date set to 09/01/2026
  • Status changed from New to Closed
  • % Done changed from 0 to 100

Listen the recording with bobby sir & noted all the points what client said and what is the work flow given by client & review the current e-commerce flow with ajit & bindu assigned some issues with them