closedDiscuss with Ravi shankar & Chandra shekar about the production issue as well as existing code base issues with new changes and clear their doubts
Files
Subtasks
Related issues
Updated by Yalavarthi Thriveni 2 months ago
- File implementation_plan.md implementation_plan.md added
- Due date set to 08/31/2026
- Status changed from New to In Progress
- % Done changed from 0 to 50
Explained client issues & what ever we discussed to day morning with sai sir & bobby sir
prepare the pricing calculation at the backend level not from frontend part for quotes as well as request & shared the implementation plan about that also
Updated by Yalavarthi Thriveni 2 months ago
- Status changed from In Progress to Closed
- % Done changed from 50 to 100
Action histories are not working as expected , so need to verify properly in all cases
Prepared retaining wall services in atlanta with different types with a document & share with sai sir