Private
Tracker *Bug Feature Support
Subject *
Description Edit As Field Staff or Admin/Manager I want to compare planned costs from the quotation with actual costs after the job So that I can see differences in usage and expenses. Acceptance Criteria For Field Staff After updating extra usage (products, equipment hours, labor hours), a dialog should show confirmation of data saved. When the Field Staff clicks Close, the dialog simply closes (no navigation). Field Staff task ends after recording usage. For Admin/Manager Admin/Manager can open the comparison view showing: Planned vs actual values (products, equipment, labor). Highlighted differences (extra usage / cost variations). When Admin/Manager clicks Close, the system navigates back to the Quotation details page. General The comparison view must show: Product Name, Planned Quantity/Cost, Actual Quantity/Cost. Equipment Hours Planned vs Actual. Labor Hours Planned vs Actual. All cost differences must be clearly highlighted. Test Scenarios Field Staff enters extra usage → dialog shows saved message → clicking Close only dismisses dialog. Admin/Manager opens planned vs actual comparison → clicking Close redirects to quotation detail page. Planned vs actual values are displayed correctly for products, equipment, and labor. Differences in cost/usage are highlighted.
Status In Progress
Priority *Low Normal High Immediate
Assignee Ajit AChandra SekharDivya Inapakurthighazala shamimJohn PatchalaKalyan RavulaKarthik PalakondaMadhu BabuMani KantaPavan Kumar MuralaRamu KodaliRavi Shankar PalleRavindra AtthotaRubanraj cSai MahanandaSai Priyatham SadineniSai Teja PopuriSravani RangannapalemSreenivas PisupatiTeja Sriram SanganiThirupathirao Uppuvinay palakondaYalavarthi Thriveni
Target version Sprint (product subscription & deliverable pre- orders) Backlog Sprint2
Parent task
Start date
Due date
Estimated time Hours
% Done0 % 10 % 20 % 30 % 40 % 50 % 60 % 70 % 80 % 90 % 100 %